In Québec in 2026, a side or rear addition typically costs $200 to $500 per square foot, a second storey $250 to $450/sq ft and an addition on piles $200 to $400/sq ft. A complete addition project often lands between $100,000 and $300,000 or more.
On top of that come plans, engineering, the permit and a contingency. Only an on-site visit gives you your real number.
The house feels small, but you love the street, the yard and the kids' school. Building an addition is often the right call. The question everyone asks first is the one that's hardest to answer online: what will it actually cost?
This guide pulls together the 2026 price ranges published for the Québec market, with links so you can check them, then covers the costs people forget and the permit rules in Montréal and Brossard. These are market averages, not our prices. Two additions of the same size can cost very different amounts depending on the house, the lot and what goes inside.
How much does a home addition cost in 2026?
The ranges below come from Soumission Rénovation (guide updated October 7, 2026) and, for kitchen bump-outs, the same publisher. Both are in French and cover Québec as a whole.
| Type of addition | 2026 price range | Keep in mind |
|---|---|---|
| Side addition or extension | $200–$500/sq ft | Depends on the foundation, number of floors and the rooms you add |
| Second storey | $250–$450/sq ft | Structural job: the existing house has to carry the new load |
| Addition on piles | $200–$400/sq ft | May not include kitchen or bathroom fixtures |
| Kitchen bump-out (micro-extension) | $30,000–$70,000 total, or $300–$700/sq ft | Small footprint, so a high price per square foot |
| Two-level addition | 1st level: $360–$480/sq ft; 2nd level: $210–$240/sq ft | Fixed costs are spread over more floor area |
| Complete addition project | Often $100,000–$300,000+ | Size, rooms and tie-ins drive the total |
Sources: Soumission Rénovation, home addition prices in 2026 and kitchen bump-out costs in 2026 (in French). Québec market ranges, not Construction Hibou's prices.
For a first ballpark, the same source suggests a simple formula: floor area × price per square foot. A 300 sq ft addition at $300/sq ft comes to about $90,000, before the costs that a quote doesn't always include (more on those below).
Types of additions and what drives their price
Side addition
A new section built against one side of the house, on one level or two. Price depends mostly on the foundation, the number of floors, how many windows it has and which rooms go in it. On a narrow lot, the municipality's side setbacks often decide how wide it can be.
Rear addition
Where the lot and the zoning allow it, the backyard usually gives the most room to work with, and it's the classic way to open a kitchen or family room onto the garden. The trade-off is a smaller yard. Soumission Rénovation prices rear extensions in the same range as side additions.
Second storey
Going up turns a bungalow into a two-storey house without giving up any yard, but it's the most structural option: the roof comes off, and the foundation and walls have to be checked for the extra weight. The main guide gives $250 to $450/sq ft. A separate article from the same source on second storeys puts the average at $200 to $350/sq ft, and over $400/sq ft for high-end work. The gap between the two is a reminder that these are ballpark figures.

Addition on piles
Instead of a poured concrete foundation, the new section sits on piles. It suits some lots and some types of additions, and it keeps excavation to a minimum. Expect $200 to $400/sq ft according to Soumission Rénovation, which may not cover kitchen or bathroom fixtures. In Brossard, the permit form then calls for a report signed and sealed by an engineer.
Kitchen bump-out
A micro-extension of a few feet, often enough for an island or a breakfast nook. Soumission Rénovation puts most budgets between $30,000 and $70,000; a simple 2 ft × 10 ft bump-out runs $25,000 to $35,000. Helical piles typically cost $2,000 to $5,000 there, against often more than $10,000 for a poured concrete foundation.
Why the price per square foot drops as the addition gets bigger
It sounds backwards, but it adds up. Some costs show up no matter the size: plans, structural calculations, getting a crew and equipment on site, the foundation and the tie-in to the existing house. Soumission Rénovation puts it plainly: small additions tend to cost more per square foot, while on a bigger footprint those fixed costs are spread over more square feet.
Two examples from the same sources:
- A kitchen bump-out can reach $700/sq ft: it still needs an engineer, new walls, a roof and an insulated floor, and the same crew has to show up for 40 sq ft as for 200 sq ft (source).
- A two-level addition: the first level is estimated at $360 to $480/sq ft and the second at $210 to $240/sq ft, because the foundation and the roof serve both (source).
The practical takeaway: if you're torn between two sizes, ask for a price on both. The extra few feet often cost less than you'd think.
Want to know where your project lands in these ranges? We'll come see the house and give you a detailed quote.
Book a consultation →The hidden costs of an addition
The price per square foot doesn't always cover everything. Here's what to add when it isn't in the quote:
- Plans and professionals: an architect or technologist, plus an engineer for the structure. For a second storey, Soumission Rénovation puts those fees at $5,000 to $12,000.
- The permit: based on the value of the work (details below).
- The foundation: soil, depth and machine access all move the price.
- Tie-ins: roof, siding, walls and floors have to meet the existing house. A new kitchen or bathroom needs connections done by licensed specialty contractors; moving a sink in a bump-out adds $3,000 to $5,000 (source).
- Moving out: for a second storey, the same source budgets 3 to 6 months of temporary housing or storage, or $6,000 to $15,000.
- The yard: repairs after heavy equipment, $2,000 to $8,000.
- Contingency: 10 to 15% of the contract.
Sales taxes come on top: GST and QST, 14.975% combined. For other renovation budgets, see our guide to renovation costs in Montréal in 2026.
Permits: Montréal boroughs vs. Brossard
An addition needs a building permit in both Montréal and Brossard, but the two cities don't work the same way.
Montréal: your borough handles it
According to the city's page on building additions, the fee is $9.80 per $1,000 of work, with taxes included in the estimate, and fees are non-refundable. The city asks for a certificate of location, a site plan of the addition, elevations and plans of every level, the building specification sheet, structural plans prepared by an engineer and a detailed quote.
In some areas, a site planning and architectural integration programme (PIIA) is required to protect the character of the neighbourhood, which adds fees and time. You apply at your borough's permit counter. For the fee math with worked examples, see our guide to renovation permits in Montréal.
Brossard: the city handles its own permits
Brossard has no boroughs. According to its permit application form (June 16, 2026 version), a residential addition costs a $51 base fee plus $3.50 per $1,000 of the estimated cost of the work, calculated before taxes with labour included. The file needs a site plan, architectural plans and, where applicable, a detailed quote, and an addition on piles or a concrete slab requires a report signed and sealed by an engineer. You file by email or in person at city hall; see the City of Brossard's page (in French) and our page on home additions in Brossard.
On the same $120,000 project, the difference is real: about $1,176 in Montréal (on the value including taxes) and $471 in Brossard (on the value before taxes). Fees change, so check them when you file. Last checked: November 22, 2026.
How long does a home addition take?
According to Soumission Rénovation, construction alone can take several months, plus design, plans, approvals and site preparation. A few reference points:
- The permit: in Rosemont–La Petite-Patrie, the city says to allow 30 to 60 days from the date the application is received. Timelines vary by borough, season and how complex the file is.
- The season: excavation and foundations are planned outside the frost period, with framing and the building envelope after that.
- The scope: a bump-out on piles is done long before a second storey, which can mean living elsewhere for 3 to 6 months according to the source.

How Construction Hibou runs an addition
Construction Hibou is an RBQ-licensed (5798-4619-01) and insured general contractor. On an addition, our job is to join the new to the old so the foundation, structure, roof and siding read as one house. Every project follows our four steps: an on-site consultation; planning (engineering plans where needed, the permit file, and a budget and schedule in a line-by-line quote); execution by our crew; and handover with a final walkthrough.
We build additions across Greater Montréal, Brossard included. See our home extension page, our page on construction in Brossard (in French) and our work in the gallery.