Renovation Permits in Montréal: When You Need One and What It Costs

Quick answer

In Montréal you need a permit as soon as the work touches the foundation, the structure or a wall, changes how rooms are divided or adds floor area. Painting, new flooring and replacing cabinets or countertops don't need one.

The permit costs $9.80 per $1,000 of work, taxes included, with a minimum of $167.40 for a residential building. Last checked on montreal.ca: November 22, 2026.

A permit can feel like red tape you'd rather skip. But it's the first thing a buyer, an insurer or a city inspector is likely to check. The good news: in Montréal the basic rules are clear and the fee is easy to calculate.

This guide sums up what the City of Montréal says, with links to its official pages. One thing to know up front: your borough issues the permit, and some boroughs add their own requirements. Off the island, cities like Brossard and Laval have their own bylaws. Before you start, always check with your borough or city.

Which jobs need a permit?

According to the city's page on interior renovations, you need a permit if the work:

Outside, every borough requires a permit to change the size of a door or window opening, or to add a new one. In some heritage areas, work on the façade may also require a site planning and architectural integration programme (PIIA).

What about finishing a basement?

In most cases, yes: finishing a basement usually means framing partitions and creating rooms, which changes how the dwelling is divided. Some boroughs go further. In Saint-Léonard, for example, the city says a permit is required as soon as the work involves drywall wall or ceiling finishes. Check with your borough. For the project itself, see our basement renovation page.

What about plumbing and electrical?

This is the one that surprises people: the City of Montréal no longer issues permits for plumbing, electrical, or electric or gas heating. That work is still governed by provincial rules and has to be done by licensed contractors; for questions, the city refers you to the Régie du bâtiment du Québec. Keep in mind that if moving a bathroom means opening or moving a wall, the wall is what triggers the permit.

Jobs that usually don't need a permit

The same city page lists minor cosmetic work that doesn't need a permit, for example:

So swapping your cabinets like-for-like doesn't need a permit. If the new kitchen moves a partition or opens onto the living room, though, the rules change. When in doubt, a question at your borough's permit counter costs a lot less than a stop-work order.

Partition framing and a staircase in a home under renovation
New partitions change how rooms are divided, so a permit is required.

How much does a renovation permit cost in Montréal?

According to the city's page on the cost of a renovation permit, the formula is: cost of the work ÷ 1,000 × $9.80. The cost of the work has to include plans and specifications, excavation, labour, materials and equipment, and taxes.

Three worked examples

Project (residential building)Cost of work, taxes includedCalculationPermit fee
Small job, one partition$8,5008.5 × $9.80 = $83.30$167.40 (minimum)
Basement or kitchen with new partitions$35,00035 × $9.80 = $343.00$343.00
Major renovation$120,000120 × $9.80 = $1,176.00$1,176.00

Calculated with the formula and minimums published by the City of Montréal. Last checked: November 22, 2026.

In practice, any residential job under $17,081.60 pays the $167.40 minimum. Other cities use other formulas: in Brossard, for instance, a residential addition costs $51 plus $3.50 per $1,000. We compare the two cities in our guide to home addition costs.

Not sure whether your project needs a permit? We'll come see it, tell you, and give you a detailed quote.

Book a consultation →

The documents you'll need

For an interior renovation, the city asks for:

For an addition the list is longer: a site plan, elevations of every façade, plans of every level and structural plans prepared by an engineer, according to the city's page on building additions.

How long does it take to get a permit?

The city doesn't publish one single timeline: it depends on the type of application, how complex it is and the season. Boroughs do give reference points:

A complete file from day one is the best way to avoid back-and-forth. A PIIA, where it applies, adds time.

The risks of renovating without a permit

According to Soumission Rénovation (in French), skipping the permit can cost far more than the permit itself:

How Construction Hibou handles permits

The city says it plainly: the person representing the construction company can file the permit application. That's what we do for our clients. As an RBQ-licensed (5798-4619-01) and insured general contractor, we coordinate plans, permits and inspections:

See our pages on residential renovation, home extensions and basement renovation, or our guide to renovation costs in Montréal in 2026.

FAQ

Your questions about renovation permits

Do I need a permit to redo my kitchen in Montréal?

Not if you're only replacing cabinets, countertops, the sink or the flooring. You need one if you change a wall, move a partition or change how the rooms are laid out. Check with your borough.

How much does a renovation permit cost in Montréal?

$9.80 per $1,000 of the cost of the work, taxes included, with a minimum of $167.40 for a residential building and $491.70 for a commercial or mixed-use building. On $35,000 of work, that's $343. Heritage areas can add fees.

Are taxes included in the declared cost of the work?

Yes. According to the City of Montréal, the cost of the work has to include plans, labour, materials and equipment, and taxes.

Do I need a permit to finish a basement in Montréal?

In most cases, yes, because you're framing partitions and creating rooms, which changes how the dwelling is divided. Some boroughs, like Saint-Léonard, also require a permit for drywall finishes. Check with your borough.

Can my contractor apply for the permit for me?

Yes. The City of Montréal says the person representing the construction company can file the application. At Construction Hibou, we prepare the file with you.